Sunday, 2 December 2012

Ready for windows

Stonework 99% complete, ready for window fitting next week
Stonework on rear complete, roof fully slated and insulation installed to sunroom
"Porthole" window to the walk in wardrobe

Friday, 26 October 2012

Stonework and window surrounds

The stonework and window surrounds make good progress
View of the back of the house, slate roofs progressing well

Monday, 15 October 2012

Ridge tiles being added to roof apexs
Chimney pots added and wall plastered

Sunday, 23 September 2012

Update

Roof ready for slating this week....
Final version of stonework style

Friday, 7 September 2012

A week on, good weather and progress

Front elevation of the house
Steelwork on the first floor
Stonework has begun
Rear view of the build
Cut roof going in...taken from the rear

Thursday, 30 August 2012

Sketches

Probably should have put these up at the start.. Sketches of front and rear of finished house

Sunday, 26 August 2012

Panorama shot from the iPad

Block work continues....

Distance shot of the build taken from near road where entrance will be...
The main part of the house...
Kitchen / diner
Living room

Sunday, 29 July 2012

Blockwork on the ground floor

Looking into the living room off kitchen, the fireplace where wood burning stove will go...
The kitchen window..
The garage roof felted and ready for slates...
The front of the house...
Back of the house looking into the kitchen\diner and sun room

Sunday, 22 July 2012

The blockwork begins...

The blockwork has began.... the garage is finished and roof trusses almost done..
Blocks placed inside house ready for blocklayers....
Blockwork has began on the wing...
Roof trusses from inside the garage...
The "CAVITY" 200mm.....